Monday, July 25, 2016

Bower Creek Bridge Construction Update

Out with the Old, In with the NEW


Construction on the bridge started promptly on July 18 with the road closure.  By noon, the bridge deck was removed and nearly all of the beams.  The contractor followed installing a turbidity barrier and driving the piles.  They then started forming the north bridge abutment, concluding the first week of work.  The north abutment should be poured with concrete later this week and work will begin on the south abutment.