CTH GV Reconstruction Begins

The reconstruction of a portion of Monroe Road (CTH GV), from Hoffman Road to the newly constructed round-about in Ledgeview (CTH G & GV) is set to begin the week of April 9th and last until approximately mid November.  Work is being completed by the Brown County Highway Department.



The four-lane highway will include a 150-foot right-of-way, 20-foot medians, bike lanes and an 8' wide side-path. The project will also include swales that will help in storm water runoff.

The county highway department is finishing engineering plans, acquiring right-of-way land and permitting. Below is the County's preliminary reconstruction schedule:

    Permitting and Bidding Structures January - April 2012
    Structure and Offline road construction August 2012
    Mainline road completion November 2012

The road will remain open to local traffic at 25 mph with a signed detour posted.

For more information on this project, or to view weekly construction updates, go to the Village's website at:  http://www.villageofbellevue.org/departments/public-works/projects-construction/county-highway-gv.html.